Let's Talk About Moving the Shared Path on Flaxton Road

Share Let's Talk About Moving the Shared Path on Flaxton Road on Facebook Share Let's Talk About Moving the Shared Path on Flaxton Road on Twitter Share Let's Talk About Moving the Shared Path on Flaxton Road on Linkedin Email Let's Talk About Moving the Shared Path on Flaxton Road link

Consultation has concluded

We have been working to finalise the design for the upgrade to Flaxton Road, including the shared walking and cycling path on the western side of the road.

While looking more closely at the detail of the upgrade, we identified there is a risk with the stability of the bank that could significantly impact the project budget.

The issues

An investigation into the long-term stability of the drain banks has shown us that the current proposal to build a shared path on the western side of Flaxton Road creates an increased risk of the path collapsing or slumping into the drain.

If the shared path were to remain on the western side, a significant length of the drain bank would need to be retained or reshaped, adding significant costs to the project. Even then, there would still be an ongoing risk of slumping or collapsing.

As well as the cost increases, even if major earthworks were carried out to stabilise the drain banks, the risks of collapse would still be a factor and the risk of ongoing repairs is high.

We propose moving the shared path to the eastern side of Flaxton Road. This avoids cost increases and removes the risk of encountering any bank stability issues. We want to know what you think about this proposal.

Tell us what you think

We’re holding two drop-in sessions at Soda Café so that you can talk more about the proposal with staff and ask questions.



We have been working to finalise the design for the upgrade to Flaxton Road, including the shared walking and cycling path on the western side of the road.

While looking more closely at the detail of the upgrade, we identified there is a risk with the stability of the bank that could significantly impact the project budget.

The issues

An investigation into the long-term stability of the drain banks has shown us that the current proposal to build a shared path on the western side of Flaxton Road creates an increased risk of the path collapsing or slumping into the drain.

If the shared path were to remain on the western side, a significant length of the drain bank would need to be retained or reshaped, adding significant costs to the project. Even then, there would still be an ongoing risk of slumping or collapsing.

As well as the cost increases, even if major earthworks were carried out to stabilise the drain banks, the risks of collapse would still be a factor and the risk of ongoing repairs is high.

We propose moving the shared path to the eastern side of Flaxton Road. This avoids cost increases and removes the risk of encountering any bank stability issues. We want to know what you think about this proposal.

Tell us what you think

We’re holding two drop-in sessions at Soda Café so that you can talk more about the proposal with staff and ask questions.



  • We'd love to hear your thoughts...let us know your feedback before Monday 21 September 2020.

    Consultation has concluded
    Share Let's Talk About Moving the Shared Path on Facebook Share Let's Talk About Moving the Shared Path on Twitter Share Let's Talk About Moving the Shared Path on Linkedin Email Let's Talk About Moving the Shared Path link